When the Minnekahta Avenue bridge reopens over the Fall River in downtown Hot Springs, a car crossing it won't feel much different. The two driving lanes on the new bridge add up to 30 feet, the same as the bridge that went up in 1948. The contracted completion date is Nov. 27, 2026, the day after Thanksgiving. In mid-October the Fall River County Herald-Star reported that completion was "still expected to be in late November."
The bridge has been closed since Dec. 15, 2025. Since then, the work and the money have gone almost entirely into the parts of the crossing a driver never sees: rock behind the abutments, the pipes under the deck, the sidewalks on either side and the pavement at each end. The deck itself is the least changed part of the job.
The new bridge is a single span, and the Herald-Star reports it will look a lot like the Jennings Avenue replacement bridge the city built in 2021. It is a little wider than the old one, and all of the extra width goes to people on foot. The north and south sidewalks grow from 5 feet to 6 feet each, and both get chain link railings on each side.
That extra foot on each side matters because of where the bridge sits. It lands at the corner of North River Street and Minnekahta Avenue, next to Kidney Springs, which is a walking corner more than a driving one.
The project is paid for through the 2023 South Dakota Bridge Improvement Grant. The state covers 80% and the City of Hot Springs covers 20%. Heavy Constructors of Rapid City holds the contract, and Brosz Engineering of Sturgis oversees the work.
When the bridge closed in December, the Herald-Star's first report said it would likely stay closed until late summer 2026. Here is the schedule Heavy Constructors laid out at the start, as the paper reported it:
By mid-May, each of those steps had slipped by several months. Pile driving was then hoped for in June, and girder setting wasn't expected before July. A Brosz Engineering spokesman explained why to the Herald-Star. The stone behind the abutments was a type that turned a planned "drilling project" into a "digging operation." Crews also had to work around a water line, a sewer line and what the paper called "a highly critical internet line" running under the decking.
Once the old deck was off, the city found more to fix. Public Works Engineer Tracy Bastian wrote to the council that the water main near the bridge was in deteriorated condition, "and original installation was not correct and posed a risk for breakage." The city is replacing that main and two old valves while the crossing is open to the sky. The council approved that change order on April 20, a net increase of just over $22,400. When Heavy Constructors damaged the sewer line under the bridge, along with some light fixtures and sidewalk around Kidney Springs, the contractor agreed to cover those costs.
City Administrator Aerial Allison explained the reasoning in the May report:
"Over the last 15plus years, City crews have made numerous minor repairs to keep the bridge operational, but its overall condition had deteriorated to the point that replacement became necessary. Similar to the road project, the work has uncovered other infrastructure that is prudent to replace while the bridge is apart, including the ductile iron water main under the bridge."
The Nov. 27 deadline has stayed in place through all of this. In December the Herald-Star had printed Oct. 27 as the deadline. Allison later said that date reflected the contractor's optimism and that the original deadline has never been extended.
Both change orders the council approved in October cover the pavement where the bridge meets the street.
| Council date | Change order | What it covers | Amount | Contract total after |
|---|---|---|---|---|
| Oct. 5, 2026 | #2 | Concrete instead of asphalt on the east approach | $10,723.71 | $1,432,809.24 |
| Oct. 19, 2026 | #3 | Added asphalt replacement on the west approach, where older pavement was near the end of its service life | $11,509.26 | $1,444,318.50 |
Both amendments are recorded in the council minutes for Oct. 5 and Oct. 19. Together they add about $22,200, close to the size of the spring water main change. The project is still described as a $1.4 million replacement, and these totals are the approved contract amounts, not a final cost.
The old bridge went up in 1948, after the June 20, 1947 flood. Its railings were the most visibly historic part of the crossing. While planning the new bridge, some council members wanted to keep them. In May the city was waiting on a quote from Heavy Constructors to modify and refinish the old railings to meet current safety requirements. The railings are no longer ADA compliant, and the grant's 80/20 split wouldn't cover the work, so the city would have paid the full cost.
By August that plan had changed. In the Aug. 17 council minutes, the Historic Preservation Commission's report says the Minnekahta Bridge railing "will be installed based on engineered design plans and the City will retain the old railing." So the new bridge gets the engineered railing, and the 1948 railing stays with the city.
The same commission report includes a request for a new walk bridge near Springs Lodge and Café. It is recorded as a discussion item. With a wider sidewalk coming on the traffic bridge, that request suggests pedestrian traffic is on the commission's mind at this corner.
Flooding along the Fall River has shaped this corner before. The Kidney Springs Gazebo at North River Street and Minnekahta Avenue was built in 1922. According to the city's Soak In Hot Springs walking tour, it is the third structure on the site because floods washed away the first two. The octagonal gazebo has eight Doric columns, exposed rafters and a warm spring-fed fountain with a plaque listing the water's mineral content. Local sculptor Mike Tuma's piece "The Gift" has sat on top since 1985, and the city restored the gazebo in 2014 with help from the Business Improvement District. The City of Hot Springs parks page describes Kidney Springs as just off Minnekahta Avenue, across from Inn By The River, with a historic bandstand and a natural amphitheater. The Fall River Freedom Trail follows the river through the middle of town and connects to Kidney Springs Park.
Springs Lodge and Cafe, at 602 Sulphur Springs Street, sits right next to the bridge. In May the Herald-Star called it the business most affected by the closure. The Wetzel family, who own the cafe, were expecting about 75 tour buses over the summer. During the closure, buses pulled into the city's Kidney Springs parking lot so passengers could get off and walk across the street to eat. Customers and buses were told to reach Minnekahta Avenue by way of 23rd Street, near the Family Dollar on University Avenue. Co-owner Vicky Wetzel told the paper she gives everyone the same reassurance about the longer drive: "Once you're here, you're here!" The cafe also promoted online ordering through its website, and customers could place an order the night before for pickup or dine-in. Wetzel said the construction company was very accommodating with the family's requests.
The City of Hot Springs runs a Minnekahta Bridge live camera feed, linked from the city's homepage, so anyone can check progress without walking down to the river. The contracted completion date is Friday, Nov. 27.
Downtown infrastructure like this bridge, its water main and the trail next to it affects everyday life on the streets around Kidney Springs. If you're thinking about a home or a commercial building near the river and want to know what has been rebuilt nearby and what the city is still discussing, Black Hills Homes & Land can walk you through it. Schedule a free consultation, and we'll go over those blocks with you.
Stay up to date on the latest real estate trends.
We are committed to guiding you every step of the way—whether you're buying a home, selling a property, or securing a mortgage. Whatever your needs, we've got you covered.